PTLT_PROJ_DEFN |
index back |
---|---|
Implementation Project Defn. |
PeopleSoft Field Name | Field Type | Column Type | Description |
---|---|---|---|
![]() |
Character(15) | VARCHAR2(15) NOT NULL |
Used in Setup Manager v2.0 for Implementation Project Name.
Prompt Table: PTLT_PROJ_VW2 |
DESCR50 | Character(50) | VARCHAR2(50) NOT NULL | Description of length 50 |
PTLT_PROJ_STATUS | Character(1) | VARCHAR2(1) NOT NULL |
The Project Status field is used in the Manage Implementation Projects page of the Setup Manager, and describes the current status of each Implementation Project that the user has created in Setup
Manager
A=Assigned C=Complete G=Generated I=In Progress N=Not Started |
IN_PROCESS_FLG | Character(1) | VARCHAR2(1) NOT NULL | In Process |
PTLT_GENERATEDDTTM | DateTime(26) | TIMESTAMP | Last Generated Date/Time |
LASTUPDDTTM | DateTime(26) | TIMESTAMP | Specifies the date and time of the last update to an entry. This field is maintained by PeopleSoft and is used in a variety of contexts. |
index back | (c)David Kurtz 2020, www.go-faster.co.uk | PeopleTools 8.58 PTRef generated on 21-DEC-20 |